More expensive with nytt thanks to the swimming pool – Hamar Dagblad

It appears in the dossier to harvest the first council meeting in Tynset.

It was in mid-June that the swimming pool was determined closed until the roof was replaced, with suggested reopen for Christmas 2016. So we had the swimming group in Tynset cancel all their swimming training sessions this fall. First in the New Year will again be offered swim workouts.

The cost of repairing the roof was initially estimated at 1.4 million excluding VAT. In a memo from the end of July is the estimate increased by NOK 300,000 to 1.7 million, excluding VAT. This means a total of 2.13 million including VAT.

The work of obtaining bids on repairing the roof is already started and the work shall be carried as quickly as possible.

– There is a hope the pool can be used at Christmas, said the cases presented to the municipal board meeting.

Damage and decay

in a report from 2011, it was noted major leaks in the transition between ceiling and wall around windows and penetrations columns ceiling. The vapor barrier is defective and the outer walls is probably not a vapor barrier.

– Wooden structures in the roof is characterized by air leakage from the swimming pool have expired in construction, it is pointed out in the report, which concludes that damage and rot under development.

As a result of this arises the danger that construction could fall down.

– Air leaks must be seen in connection with the pool temperature is increased from 22 degrees to 33 degrees through the basin 50 -Year life, the report said. Tynset points out that the basis of this status report as they regularly assessed the condition of the pool roof.

– Spring 2016 was the state so that a basis of a safety evaluation found it appropriate to make carry out a new assessment of the roof pointed the. The assessment of Norconsult AS granted on the 10th June this year. Where it was concluded that ceiling, with the exception of prefabricated columns and beams of concrete, should be replaced as soon as possible.



Billigst to renovate

In case evaluation of politicians it is recalled that the current swimming pool in Tynset is about 50 years old and it has only been a matter of time before the system had to be renovated. Shortcomings apply the structural, treatment plant and the technical facilities.

In a report that the council dealt with in 2012, it emerged that the cost of retrofitting of current pool versus building a new heating pool (12.5 meters) would be approximately the same.

– If one chooses to build a new heating pool requires that existing pool demolished and turned into another local, said the legal assessment, pointing out that the existing pool is an integral part of the physical education building and this therefore will incur substantial additional costs.

therefore, it is concluded that renovations are far less expensive than construction of a new 12.5-meter pool.

– A changing of only roofs and the remaining renovation taken later is neither prevents or complicates later renovation of the pool or a possible construction of a new 25-meter pool, according to the legal assessment.

it is proposed that the repairs be financed using retained earnings, which balance at year end was on just under NOK 23 million.